Slow Going

Rock tells me I need to set my clock to construction time. It is a hard thing for me to do. The things that were supposed to be done on Friday were not. No one worked the weekend and then it rained on Monday. In the satellite business that is 3 lost days. In construction time that is the way it goes. I hope ray has the patience for putting up with me. Perhaps this is my own road to patience... or a heart attack.
After pushing week after week on getting barn plans completed we may have the plans into the county tomorrow and the barn parts delivered next week. Then it will be waiting for the permit. Great... more patience training.